A Major Infrastructure Upgrade for Clifton: Inside the City’s New Modular Water Treatment Plant

  • Feb 6
  • 3 min read

Clifton Breaks Ground on Tennessee’s First Modular

Water Treatment Plant — And We’re Proud to Have

Helped Lay the Foundation

The City of Clifton has officially taken a major step forward with the groundbreaking of

Tennessee’s first modular drinking water treatment plant — a project that will significantly

improve water quality, reliability, and long-term capacity for the community.


For a small town like Clifton, this isn’t just another construction project. It’s a long-term

investment in public health, infrastructure stability, and future growth. Coop & Berry Land

Prep TN was honored to play a role in the early stages of this important work by completing the

site preparation and earthwork needed to get the project started.


What the New Clifton Water Treatment Plant Will Do


The new facility is designed as a modular, future-ready water treatment plant, meaning it can

be expanded over time as demand increases. Instead of rebuilding from scratch years down the

road, the City of Clifton will be able to add capacity in phases — saving money and reducing

disruption.


Once complete, the plant is expected to treat up to 1.5 million gallons of drinking water per

day, drawing from the Tennessee River. It will use advanced ceramic membrane filtration

technology and modern treatment systems designed to improve water quality and help remove

contaminants, including PFAS compounds that have raised concerns nationwide.


This project also includes:


● A new intake structure and raw water transmission lines

● Finished water lines for distribution

● High-service pumps and a clearwell

● Electrical, control, and laboratory spaces

● Parking, access drives, and supporting infrastructure


Together, these upgrades will provide Clifton with a more reliable, safer, and more resilient

water supply for decades to come.



Funding and Long-Term Impact for the Community


The project is supported by funding through the Tennessee Drinking Water State Revolving

Fund, including a low-interest loan and loan forgiveness made available to help disadvantaged

communities complete critical infrastructure improvements.


For Clifton residents and businesses, this investment means:


● Improved drinking water quality

● Reduced risk of outages or system failures

● Infrastructure that meets modern regulatory standards


● Capacity to support future residential and commercial growth


Reliable water systems are foundational to any community, and this project helps ensure Clifton

is well-positioned for the future.

Our Role: Site Preparation & Early Groundwork


Before construction of the treatment plant itself could begin, the site needed to be properly

prepared to support a complex public utility facility.


Coop & Berry Land Prep TN began work on the project in November 2025 and completed our

scope in early 2026, ahead of vertical construction. We were brought onto the project by

Bowen Engineering, the engineering firm awarded the project, after building a strong local

reputation for dependable excavation and site work.


Our scope included:


● Clearing the project area

● Mass grading to establish proper elevations

● Rough grading of topsoil for the facility footprint

● Hauling off excess material

● Erosion control to protect surrounding land and waterways


Proper site preparation is critical for infrastructure projects like this. Stable grades, controlled

runoff, and well-prepared building areas help ensure that everything built afterward — from

foundations to utilities — performs as designed for the long haul.



Why Local Experience Matters on Projects Like This

Public infrastructure projects demand attention to detail, accountability, and an understanding of

local conditions. Middle Tennessee terrain brings its own challenges — from clay-heavy soils

and elevation changes to drainage and river-adjacent work.


As a local contractor, we understand those realities and approach each project with the

responsibility it deserves. We believe it’s a blessing to be able to contribute to infrastructure that

protects public health and serves future generations, especially in communities we live and work

around.

Looking Ahead for Clifton and Middle Tennessee

The Clifton modular water treatment plant represents more than new equipment and buildings

— it represents preparedness, growth, and stewardship. We’re proud to have been trusted

with the early groundwork that helped get this project off the ground, and we look forward to

seeing the positive impact it will have on the city for years to come.

At Coop & Berry Land Prep TN, we’re grateful for opportunities to support projects that

strengthen Middle Tennessee communities. Whether it’s municipal infrastructure, utility work, or

site preparation on rural land, we’re committed to doing the job right from the ground up.



Need a Driveway, RV Site, or Property Improvements?

Coop & Berry Land Prep TN specializes in excavation and land development projects including driveways, RV pads, drainage work, clearing, and grading. We focus on durable results, clean execution, and clear communication from start to finish.

If you’re ready to improve your property or want a professional opinion before starting, we’d be glad to help.

Contact us to schedule a site visit or get a quote.

Proudly serving Clifton, Tennessee

615-977-1626

 
 
 

Comments


Garden Soil
Call us now
!cid_ii_mhyx7w8r0.png

Coop & Berry LandPrep TN

150 Elm Street, Clifton TN 38425

FOLLOW US ON

  • LinkedIn
  • Facebook
  • Instagram
Garden Soil

Get In Touch Here:

Lets Make This Easy

© 2023 by LandPreptn.com. All Rights Reserved.

bottom of page